Report
07.12.2010
Reference: E10-ENM-22-04

ERGEG Opinion on the ENTSO-E Pilot Community-wide Ten-year Electricity Network Development Plan

This ERGEG opinion provides views on ENTSO-E's pilot Community-wide Ten-year Electricity Network Development Plan (TYNDP). It is based on the requirements defined by ERGEG in its June 2010 Advice on the TYNDP (E10-ENM-22-03). The opinion suggests a number of improvements to the TYNDP, ahead of the preparation of the first official Community-wide TYNDP in 2012. The regulators' review is done in accordance with the legislative requirements in the 3rd Package and as guidance for ENTSO-E work in this area.